Hengde mold temperature controllers are widely utilized in a diverse range of industries. Such industries encompass plastic & rubber manufacturing, the chemical field, electronic production, food & beverage, the wood board industry, die casting, printing, and many others.
How to maintain it? Hengde mold temperature controller maintenance is mainly divided into daily inspection and regular maintenance.
Daily Inspection:
1. Check the mold temperature controller housing and control panel to keep them clean and dry, and avoid using detergents containing acidic and alkaline substances to wipe stains. When wiping the inside with a rag, pay special attention not to damage the electrical parts.
2. Check whether each component is normal, such as checking whether the temperature display of the mold temperature controller is normal, checking whether the parameter setting of the controller has changed; whether there is leakage at the pipe connection, and check whether there is liquid dripping or moisture at the joint. Observe whether the oil pump, water pump and other running parts have abnormal noise or vibration. The sound should be stable and there is no obvious shaking during normal operation. Check whether the cable is damaged or worn, and replace it in time if necessary.
Regular Maintenance:
Perform in-depth maintenance on the mold temperature controller every certain period of operation (according to the requirements of the equipment manual). The following is the maintenance time of each accessory:
Item | Maintenance Period | Maintenance |
Solenoid valve | 1 month (actual operation 600 hours) | Dismantling and cleaning |
Liquid level switch | 1 month (actual operation 600 hours) | Dismantling and cleaning |
Mold connection hose | 1 month (actual operation 1200 hours) | Dismantling and cleaning |
Noise / strange smell / heat | Every day | No Noise / Vibration |
Loose terminals | 3 months | Inspect and tighten |
Dust and garbage in control cabinet | 1 month | Clean |
Electromagnetic contactor (Pump) | 3 years | Replace |
Liquid level display tube | Every day | Check for proper amount |
Heat transfer oil | 6 months |
Replace |
PC board | 3 years |
Replace |
Pump | 1 year(Every day) |
Confirm noise |
Pipeline | 1 month |
Check and confirm no oil leakage |
Special Precautions:
1. It is best to clean the equipment return filter once a month. After the test machine is completed, it is best to clean it several times before normal use.
2. Tighten the screws of all electrical parts of the equipment once a month (especially the contactor, because the long-term operation of the mold temperature controller may cause the screws to loosen);
3. Before shutting down, it is recommended to lower the temperature of the water mold temperature controller to below 40℃ and the temperature of the oil mold temperature controller to below 80℃ before shutting down, which can extend the service life of the pump and heating tube.
4. If the customer's equipment pipeline is higher than the oil tank of the Hengde mold temperature controller, the oil tank can be raised, or the inlet and outlet valves can be turned off first, and then shut down to prevent backflow when the circulation pump is not working.